Herman Mashaba, Johannesburg’s mayor since Friday, visited Brixton Reservoir on Sunday 29 November for a briefing with Johannesburg Water’s senior managers on the city’s water supply problems.

TimesLIVE reported that Mashaba said the visit was to understand why supply keeps failing and how to fix it. The city outlined a list of reservoirs and pump stations still under repair or upgrade.

What the briefing covered

According to TimesLIVE, Mashaba gave the status of four sites:

  • Crosby Reservoir is supplying water, but its levels are low. The backup pump station is finished and running, while equipment for the main pump station is still being bought.
  • Brixton Reservoir has a new reservoir and water tower, both in use, which raises how much water the area can store.
  • Hursthill 1 Reservoir was taken out of normal operation because of structural defects. Residents in higher-lying areas have low pressure or no water. A contractor is appointed and repairs are due to start in January 2027.
  • Hursthill 2 Reservoir is limited to about 40% of capacity by structural damage. Repairs are 48% complete.

Construction at the Hector Norris Pump Station is 98% complete. TimesLIVE reported that once it runs, the station is expected to improve water distribution.

The promises behind the visit

In his speech to councillors after Friday’s vote, Mashaba listed four priorities, according to TimesLIVE: basic services, failing infrastructure, hijacked buildings and law enforcement. He said his administration would work to rebuild public trust and make sure residents get the services their taxes pay for. TimesLIVE quoted him saying residents “want us to get on with the work”, naming water in the taps first among the services residents want.

Johannesburg water projects, share complete
Hector Norris constructionHector Norris construction: 98%98%Hursthill 2 repairsHursthill 2 repairs: 48%48%
Hector Norris constructionHector Norris construction: 98%98%Hursthill 2 repairsHursthill 2 repairs: 48%48%

Source: Johannesburg Water briefing, as reported by TimesLIVE. Chart: Rand Desk

Our earlier story on how Mashaba won the Johannesburg mayoral vote has the votes and the parties behind them. This piece follows only the water briefing, which TimesLIVE reported on Sunday, and it adds no figures beyond that report.

Put side by side, the briefing’s figures show where each site stands. One reservoir is out of normal use until repairs begin. A second works at 40% of capacity, with its repairs 48% done. A pump station is two percentage points from completion.

The TimesLIVE report gives no cost for the repairs, no completion date for Hursthill 2 and no date for the Hector Norris station to start running.

The next marker in the reports is January 2027, when the contractor is due to begin repairs at Hursthill 1 Reservoir.