Eskom said on 13 November that South Africa had gone 546 consecutive days without load shedding, up from 504 days on 2 October.

SAnews reported the figure on 16 November from Eskom’s statement of the previous Friday. The count starts on 16 May 2025, so the run is about a year and a half long. We have used only figures Eskom published, and the 13 November and 2 October ones come through SAnews, not Eskom’s own pages.

What changed in six weeks

The count was 504 days on 2 October and 539 on 6 November. Over the same period, Eskom reported these changes:

  • The financial year-to-date Energy Availability Factor (EAF) moved from 68.11% to 68.16% and then 68.2%.
  • Spare generation capacity above demand was about 6,855MW on 6 November and about 6,933MW on 13 November.
  • Diesel spending since 1 April went from R1.16 billion on 1 October to R1.26 billion on 5 November and R1.27 billion in the latest statement. A year earlier the comparable figure was about R6 billion.
  • Customers on load reduction fell from 202,590 to 102,551, a drop of 100,039, or about half.

The weekly EAF is not always better than last year’s. Between 30 October and 5 November it was 69.53%, against 70.66% in the same week of 2025, Eskom said in its 6 November statement. The year-to-date figure was 68.16%, against 63.21% in the same period last year.

Load shedding and load reduction

The two are different. Load shedding is the national scheduled cuts that the count measures. Load reduction is Eskom limiting supply in high-risk areas, where it says illegal connections and meter tampering damage infrastructure. Eskom said seven of the nine provinces are now free of it.

Consecutive days without load shedding, per Eskom statement
0200400600 days2 Oct6 Nov13 Nov2 Oct: 504 days6 Nov: 539 days13 Nov: 546 days546 days
0200400600 days2 Oct6 Nov13 Nov2 Oct: 504 days6 Nov: 539 days13 Nov: 546 days546 days

Source: Eskom statements of 2 October, 6 November and 13 November 2026, via Eskom and SAnews. Chart: Rand Desk

Eskom described the programme to end load reduction as phased. It covers 971 feeders and about 1.69 million customers out of a customer base of 7.2 million. Its target is March 2027.

Our explainer on how load-shedding stages work sets out what each stage would mean if cuts return. Our 7 November story on Eskom’s diesel bill and availability has the diesel figures in more detail.

What happens next

On 2 October Eskom promised a Summer Outlook within weeks, and we have not found one in the statements we have read. The next weekly updates will show whether the count keeps growing. Eskom put unplanned outages at 18.93% of capacity for the year to 5 November, 6.05% lower than a year earlier.