Eskom said on 10 November 2026 that Koeberg Unit 2 has passed the Integrated Leak Rate Test, which checks that the reactor’s containment building does not leak.
The test is carried out every ten years and is mandatory under the station’s licensing requirements, Eskom said. An internationally recognised utility analysed the results independently, and according to Eskom, Unit 2 “met all required acceptance criteria”. Eskom did not name that utility or publish the measured leak rate.
The containment building is one of the station’s main safety barriers. Eskom described it as designed to stop an uncontrolled release of radioactive material in the event of a nuclear accident, which it called highly unlikely.
Bheki Nxumalo, Eskom’s group executive for generation, said the nuclear teams at Koeberg “continue to meet the rigorous global standards and schedules” for the station’s operation. He said Koeberg delivers some of the lowest cost per unit of energy in Eskom’s fleet.
Where the unit stands
Unit 2 is in an outage. Eskom said its outage and maintenance work will carry on as planned before the unit returns to service, and gave no date. Eskom’s November 2025 statement put the unit’s contribution to the grid at 946MW at that time.
The same test was completed on Unit 1 in July 2025, Eskom said, and that unit continues to operate.
The licence behind the test
The National Nuclear Regulator approved a 20-year licence extension for Unit 2 in November 2025, to 9 November 2045. Unit 1 received its extension on 15 July 2024, to 21 July 2044. Eskom said both units together supply 1,860MW.
In November 2025 Eskom said the extension followed a refurbishment and life-extension programme that included the replacement of three steam generators, safety inspections and refuelling. Eskom also said Unit 2 had run at 100% energy availability for 241 consecutive days that year.
Eskom said the licence extensions support the Integrated Resource Plan 2025, which recognises the role of nuclear energy. Eskom’s statement last year said keeping Koeberg running avoids the need for immediate large-scale replacement capacity.
Eskom’s proposal for a new nuclear plant at Thyspunt is separate from Koeberg. The environment department accepted its scoping report, as we reported in Thyspunt nuclear plant moves to full environmental assessment. Eskom’s wider performance is covered in our report on Eskom’s diesel bill and energy availability.
The next step is Unit 2’s return to service, for which Eskom has given no date.