Transnet expects the container backlog at Durban to last into January, its group chief operating officer said on Monday. The Durban Gateway Terminal (DGT) could take up to three more years to reach full speed.
Solly Letsoalo told Business Day, in a report carried by TimesLIVE, that the terminal is sitting on a queue of roughly 10 or 11 vessels a day that cannot berth as soon as they arrive. EWN reported that up to 14 vessels are waiting. Letsoalo said the retail rush adds about two months of work on top of that.
TimesLIVE reported that the improvement since August “won’t take us out of the backlog in December”, in Letsoalo’s words. He expects a drop in January as the peak season passes.
How the backlog built up
International Container Terminal Services (ICTSI), a Philippines-based operator, took over DGT in January under a 25-year concession, according to TimesLIVE. ICTSI holds 49% and Transnet 51%. The terminal and Pier 1 together handle 65% of South Africa’s container volumes.
The queue began in August, when a new operating system glitched. Letsoalo told Business Day that the failure came at the peak of the citrus export season, “and that backlog has never been recovered”. The Citrus Growers’ Association has said logistics delays caused missed market windows in the 2026 export season, TimesLIVE reported.
Transnet cleared the car industry first. Letsoalo said no containers for the auto sector were waiting to be offloaded as of Monday.
Medicines and festive stock
IOL reported that Transnet has 41 medicine containers on a priority list from the Department of Health. Eighteen have been delivered and seven are due between 23 November and 2 December. Sixteen more have not yet been nominated by shipping lines for berthing.
Letsoalo told Business Day that no ship carrying urgent pharmaceuticals is stuck at the port, and that ships still to come have left India and Rotterdam. He said Transnet does not know whether those orders were placed late. TimesLIVE reported that Parliament heard last week that health minister Aaron Motsoaledi had asked transport minister Barbara Creecy to help release held shipments.
Retailers are exposed too. Pepkor said this week that port problems were likely to remain a headwind for trading in the near term, and Mr Price has said it is managing supply chain disruption, according to EWN. Our report on Pepkor’s warning has the group’s figures. Letsoalo said most festive products are already on shelves because retailers order well ahead.
What comes next
Equipment is the long fix. ICTSI is bringing in new equipment, including ship-to-shore cranes, and second-hand equipment of the current design, while it reconcretes the terminal surface so it can use rubber-tyred gantry cranes. Letsoalo said the first phase should be finished in about a year and a half, and that the terminal will live with the less efficient equipment for the next three years.
Transnet disputes that ICTSI inherited a broken operation. It says average ship turnaround at the terminal improved from about 105 hours in April 2025 to about 97 hours in December while Transnet still ran it, a figure we covered in Transnet’s own account of Pier 2. Our earlier story sets out the measures Transnet announced on 18 November.
Logistics consultant Evert de Ruiter, a former Transnet executive, told EWN that ICTSI’s due diligence only began once it was already running the terminal, because a rival bidder’s court challenge held up the deal for almost two years.
The next marker is January, when Transnet expects the queue to shorten.