Durban port delays bring container charges from US$1,000 a day
A cable maker says container discharge at Durban now takes 7 to 14 days, against about three before, with shipping-line charges from about US$1,000 a day.
South Africa's news, from the source
The state freight rail, port and pipeline company, and the logistics reforms that decide how fast goods move.
A cable maker says container discharge at Durban now takes 7 to 14 days, against about three before, with shipping-line charges from about US$1,000 a day.
Transnet's group chief operating officer says the Durban Gateway Terminal has 10 or 11 ships a day waiting to berth and needs up to three years to reach full speed.
The owner of PEP and Ackermans reported revenue of R105.9 billion for the year to September, and said port delays are expected to weigh on trading.
Transnet says ship turnaround at Pier 2 improved from 105 to 97 hours in 2025, while IOL reports vessel waits of 14 to 20 days now.
Transnet says all six Pier 1 cranes are available from 21 November, while the health department waits on 30 shipments of medicine.
The train returned on 2 November with 2,991 tonnes, and SAnews reported that Grindrod plans to move about 288,000 tonnes of coal in its first year of commercial service in 2027.
The government's second-quarter reform report says Transnet earned R4.6 billion in the year to March 2026, against a R1.9 billion loss a year earlier.
At the Durban Chamber's 170th dinner on Wednesday the president said eThekwini employment is up 90,000 in a year, six days before the 4 November election.
Kumba produced 7.5 million tonnes in the third quarter, but sold 10.0 million by running down stockpiles, and kept its full-year targets.
The yearly shutdown of the 861km railway runs to 16 October, and the Budget Facility for Infrastructure is paying R1.5 billion of this year's maintenance bill.